Illustrative image – not actual.ProjectsToday exclusively brings to you, the current status of various projects awarded to India based companies in the month of July 2010.
- Leighton Contractors India in consortium with Sterlite Industries bagged
had an order worth Rs 230 crore for widening the existing 350 mtrs long
general
cargo berth by 21 mtrs for coal unloading. Work on the project was
underway with completion scheduled for June 2014.
- GEI Industrial Systems has begun the supply of air cooled steam condensers
for Ind-Barath Power's
450 MW coal based power project at Swaminathan Village, Vatapedaram Taluka
in Tuticorin district of Tamil Nadu. The entire project is to be completed by
December 2011.
- GEI Industrial Systems has also begun supply of air cooled steam
condensers for Shree Renuka Sugars'
45 MW co-generation power unit at Bharapar, Gandhidham in Kachchh district
of Gujarat.
- Work on the residential complex 'Nitesh Hyde Park' at Hulimavu village, Bannerghatta Road in South Bangalore district of Karnataka is underway. Ramky Infrastructure was appointed the contractor for the project by Nitesh Housing Developers.