Cuddalore refinery might be relocatedIllustrative image – not actual.

The six million tonne Rs.3480 crore Nagarjuna oil refinery at Cuddalore in Tamil Nadu might be relocated. The promoters of the company, the Nagarjuna Group, are having talks with the Andhra Pradesh state government for sales tax benefits, in order to make the project viable The project also might be relocated outside India, with Bangladesh and Sri Lanka being the two present options.

 

The project has been in a state of flux over the past five years, and has not been able to achieve financial closure. The project envisages the setting up of a refinery by dismantling and moving of a second-hand German refinery into India. By present thinking, the project is likely to be commissioned by 2005.

 

Progress of Cuddalore Refinery:

 

Fifty per cent of the 1,000 acres of land has already been acquired. The company has completed contour and traverse surveys and the soil investigation is in progress. ABB Lummus of Switzerland, Krupp Uhde of Germany and Uhde India have bagged engineering contracts. ABB Lummus would do the basic engineering services, procurement, construction and project management for the refinery. The dismantling and relocation of the refinery in Germany is expected to commence by March 1999 and would be engineered by Krupp Uhde. India would do the detailed engineering of the project, which would be carried out after the relocation.


In August 1999, the project received NOC from the Tamil Nadu Pollution Control Board. Dismantling of the refinery in Germany was in progress and all the equipments are expected to reach the site at Cuddalore by June 2000. (Hindu 26/8/99)


The company has entered into a technical collaboration with Institute Francais du petrole of France for its proposed diesel upgrade the unit at the refinery complex. The company has received all clearances for this technical tie-up. (OBP 21/2/00)

 

As of September 2000, an expenditure of Rs.410 crore was incurred on the project.

 

In June 2001, the project received clearance from the Union Ministry of Environment and Forests.

 

In September 2001, Indian Oil Corporation had abandoned its plan to become a strategic partner in the project. As the company has already access to market products in Southern India from the newly acquired Chennai Petroleum Corporation (CPCL).

 

The construction work on the refinery is likely to commence in the first quarter of 2002.

 

As of March 2002, all the necessary approvals for implementation had been obtained and NOCL was in the process of tying up its equity for achieving financial closure. The company has invested over Rs.530 as on 31 March 2002.

 