Illustrative image – not actual.Cuddalore PowerGen’s coal-based thermal power project is running into trouble, as the company has failed to achieve financial closure.
Cuddalore PowerGen is seeking an extension of the deadline for financial closure for the fifth time.
Further, Tamil Nadu Generation and Distribution Corporation (TANGEDCO) has said that it is not interested in Cuddalore Powergen’s 1,320 MW project (the utility has a power purchase agreement (PPA) with the company) as the state is ‘power surplus’.
Cuddalore PowerGen is a project promoted by BGR Energy with a proposed investment of Rs 6,200 crore. The company entered into an agreement with TANGEDCO in 2008 with a schedule to achieve financial closure in 12 months. However, the deadline has been extended several times.