Illustrative image – not actual.Castle Rock Construction Company (CRCC) is setting up temporary concrete batch plant.
CRCC plans to remove 233,554 sq yards (or nearly 48 acres) of pavement, 475,326 cub yards of dirt and put down 307,802 sq yards of new concrete pavement, requiring 100,000 cub yards of concrete, 150,000 tonne of rock and sand and 27,000 tonnne of cement and flyash.
The company has purchased a 45-acre parcel of vacant land near the southeast corner of the Hospital Road/I-76 interchange outside of Brush, and during a recent special session of the Brush City Council, a special use permit was approved to allow Castle Rock Construction to set up the concrete batch plant which will provide concrete for the construction, which will be active for the next two years.
Source: The Fort Morgan Times