Illustrative image – not actual.Costs plans build a South Carolina plant to convert weapons-grade plutonium into fuel for nuclear reactors.
The project is estimated to cost $3 billion, exceeding estimates by more than 50 per cent. The plant built by a Shaw Areva MOX Services LLC consortium that includes Paris-based Areva SA (AREVA) also won’t open until November 2019, more than three years later than the October 2016 target.
Source: Bloomberg