Illustrative image – not actual.As
a result of effective monitoring, the overall cost overrun in central sector
projects costing Rs.20 crore and above has come down from 62 per cent in March
1991 to 21.9 per cent in December 2002 with respect to their original approved
costs.
According to the latest available Project Implementation Status Report on
central sector projects prepared by the Ministry of Statistics & Programme
Implementation, power, mines and steel sectors have performed better while the
performance of civil aviation, atomic energy, railways, urban development and
shipping & ports sectors have been worse.
The Report covered 548 projects including 39 mega projects (costing Rs.1000
crore and above), 241 major projects (costing between Rs.100-1000 crore) and
268 medium projects (costing between Rs.20-100 crore). The anticipated cost of
these projects is Rs.2,16,263 crore. The total expenditure till December 2002
was Rs.71,638 crore which is about 33.13 per cent of the total estimated cost
of the projects included in the Report.
Against an approved outlay of Rs.31,466 crore for the year 2002-2003, the
expenditure during the first three quarters was Rs.15,860 crore. Mega and major
projects account for about 51 per cent of the total number of projects and
about 93.75 per cent of the total anticipated cost. Initially 105 projects were
scheduled for completion in the year 2002-03. Later 70 projects were added with
dates of completion by March 2003. Out of the 175 projects due for completion
during the year, 43 have been completed.
Time and cost overruns have been a major problem affecting the central sector
projects. The study shows that during the year only 23 out of the 178 delayed
projects have contributed nearly 90 per cent of the total cost overruns.
The quarterly review of the project enables the Government to identify the
constraints and helps to resolve the problems affecting the implementation of
the projects. In-depth critical review of the progress by the Administrative
Ministry with the Project Authorities and follow up with the State Governments
enables the Government to minimize delays and cost overruns in completing the
projects.