Cost overrun for 340 infrastructure projectsIllustrative image – not actual.
As many as 340 infrastructure projects, each valuing Rs 150 crore or more, have shown cost overruns to the tune of more than Rs 3.3 lakh crore owing to delays and other reasons.

The total cost of implementation of 1,405 projects was Rs 18,09,681.47 crore, while their anticipated completion cost is likely to be Rs 21,39,924.38 crore. This will result in an overall cost overruns 18.25 percent of the original cost to Rs 3,30,242.91 crore.

The projects are delayed owing to land acquisition, forest clearance and supply of equipment, fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, among others.

The ministry monitors infrastructure projects worth Rs 150 crore and above. Of these, 1,405 projects, 340 reported cost overruns and 381 time escalation.  

The expenditure incurred on these projects till March 2019 is Rs 8,53,680.47 crore, which is 39.89 percent of the anticipated cost of the projects.  

Of the 381 delayed projects, 117 projects have overall delay in the range of one to 12 months, while 63 reflect delay by 13 to 24 months, 103 are delayed of 25 to 60 months and 98 projects show 61 months and above delay.

The average time overrun in the above delayed projects is 43.17 months.