Cost of Subansiri project escalates Illustrative image – not actual.

The total cost of NHPC's Lower Subansiri project at Gerukamukh in Dhemaji district of Assam has escalated by about Rs 1,200 crore due to the delay in implementation of the work, and other issues as well.

 

The project cost has moved up due to forced suspension of work since December 2011, following agitation by a section of stakeholders, on the grounds of safety-related aspects and downstream impact.

 

NHPC has already invested about Rs 6,600 crore in the project, with 8 x 250 MW capacity. There is a recurring expenditure of Rs 50 crore every month due to work stoppage and any more delay will further increase the cost.

 

Assam will get around 533 MW of power, which is more than 25 per cent of the total power, valued at about Rs 600 crore.

 

According to the company, based on the study of the Expert Group and other committees, issues have been resolved. NHPC has assured it will implement the modifications proposed by the Dam Design Review Panel set up under the directions of the Thatte Committee.

 