Illustrative image – not actual.The total cost of NHPC's hydel power project at Hapoli (Ziro) in Lower Subansiri district of Arunachal Pradesh is likely to be increased more than initially envisaged.
The cost of the project may escalate to around Rs 12,000 crore, following delays on account of various hindrances.
The project, with 2,000 MW (8 x 250 MW) capacity was estimated to cost Rs 6,285.33 crore in August 2003. Then, in May 2008, the cost of the project increased to Rs 7,451.99 crore.
Local issues, contractual issues, geological surprises, delay in decision making and poor risk-taking assessment have impacted the progress on the project, which is now likely to cost nearly Rs 12,000 crore. The project has been stalled since December 2011, after the local people raised issues related to its safety and downstream impact.
Besides, the state is expected to get 25 MW or more free power from the plant which is likely to resume construction work from December 2013. The project, earlier expected to be fully commissioned by December 2012, is now likely to be operational by December 2017.
The project envisages construction of a 116 mtr high rockfill dam, headrace tunnel, steel lined penstocks, surge shaft, surface power house and tailrace tunnel.