Illustrative image – not actual.The project cost of the 33.5 km underground Colaba-Bandra-SEEPZ line of Mumbai Metro Rail Corporation (MMRC) has increased by almost 50 percent. The estimated cost of the project was Rs 23,136 crore and Japanese International Cooperation Agency (JICA) was funding 57.2 percent of the total cost. The hike is in the cost of civil construction which is yet to be awarded.
The project cost has increased because of the fluctuation in rupee-dollar value, increase in service tax from 10.3 percent to 14 percent and the change in the deemed export category list by the Directorate General of Foreign Trade, which has affected procurement of material for metro rails in India.
The date for awarding the order of civil construction work has been rescheduled by end of November 2015.