Illustrative image – not actual.As per the draft proposal by the water supply department, the project cost is estimated at Rs 2,615 crore.
The work involves laying the 1,700 km pipeline network, installing meters, and upgrading the water treatment plants.
On 3 August 2017, the PMC administration had scrapped the earlier tender process which had estimated the cost of the project at Rs 2,818 crore. The bidders had quoted 25 percent more than the estimated cost.
The PMC had decided to raise funds for the project through municipal bonds, which included supply, installation, and commissioning and operation cost of the project.