Illustrative image – not actual.The road from Panipat in Haryana to Jalandhar in Punjab is likely to run into cost overruns due to rescheduling of its commission date.
The 291-km long road from Panipat in Haryana to Jalandhar in Punjab is likely to run into cost overruns of Rs 1,180 crore. The anticipated cost of the Panipat to Jalandhar stretch of the highway project may touch Rs 2,288 crore as against the original estimated cost of Rs 1,108 crore. The project is also likely to have a time overrun of 21 months. The original date of commissioning of the project was November, 2011 which has now been extended to August 2013.
The project is delayed due to delay in supply of stone aggregate due to ban on mining, removal of encroachments, land acquisition problem, delay in approval of design from Railways, relocation of the toll plaza etc.