Core Green Sugar & Fuels to achieve financial closure for Gulbarga plantIllustrative image – not actual.

Core Greeen Sugar & Fuels is likely to achieve financial closure for setting up sugar unit at Gulbarga district of Karnataka by July 2007. Civil work will commence thereafter. Environmental clearance is also expected by next month. PPA is likely to be signed by August 2007.

The sugar plant,l spread on 300 acres of land and will be implemented in two phases. It involves an investment of Rs.300 crore. Phase I will include 5,000 tccpd sugar unit along with 20 MW co-generation power plant. Phase II will comprise only distillery unit with a capacity of 50,000 klpd. Mitcon is in the process of preparing the detail project report.