construction of a flyover at Andheri in Mumbai, which had been hanging fire for
almost two years on account of various hurdles, is finally expected to be
completed by June 2001.
Work on the controversial flyover had first begun in October 1997. It was then targeted for completion by December 1999. However, in April 1999, the project was stalled following differences of opinion between the Government and the builder (Jog Engineering Ltd) on one side and environmentalists on the other, on the issue of commercial exploitation of the space underneath the flyover. Delayed payments by the State Government’s Public Works Department had further compounded the problem.
Work on the flyover had restarted in
the first week of October 2000. It may be noted that although construction work
has resumed, no decision has been taken on the commercial space beneath the flyover.
It is proposed to have two
ground-level parking lots and three basement parking spaces spread over an area
of 1 lakh square feet. These can accommodate nearly 635 cars. The project also
entails construction of three pedestrian subways at the Sahar, Gold Spot and
Andheri-Kurla junctions.