Contractors seek early completion of dredging work at JNPTIllustrative image – not actual.

Overseas contractors consisting of a team of Belgian and Dutch dredging contractors have requested the Jawaharlal Nehru Port Trust (JNPT) to be allowed to complete the dredging work a year earlier.

The contractors were hired to deepen the channel of JNPT to 15 mtr from 14 mtr. The project will entail an investment of Rs 1,966 crore.

The dredging work, which started on 1 September 2017, is to be completed by March 2019 according to the tender.

The revised schedule was sent by the dredging contractor in October 2017 to complete the work by March 2018.

Tata Consulting Engineers, the independent engineer for the project, evaluated the early completion request and concluded that it was not advisable on financial and feasibility parameters.