Contract for Kuttiyadi hydel power project not yet awardedIllustrative image – not actual.

The Kerala State Electricity Board (KSEB) has not yet awarded the contract for the 100 MW Kuttiyadi hydel power project proposed to come up in Kozhikode in Kerala.

 

In 2000, 4 pre-qualified bidders had submitted their bids for the project. The bidders included the consortium comprising Bharat Heavy Electricals - Larsen & Toubro, which quoted Rs.150 crore, Tractebel of Belgium (Rs.170 crore), CEHEC of China (Rs.285 crore) and SNC Lavelin of Canada (Rs.327 crore). However, the last 2 bidders opted out of the project, while the bids of the first 2 were not accepted by KSEB.

 

Now, its been 2 years since indecision hangs over the project, which was proposed to be commissioned within 42 months. The delay in project implementation has led to cost escalation.

 

According to reports, the indecision is a consequence of internal strife in KSEB.