Illustrative image – not actual.According to unconfirmed press reports, the Himachal Pradesh government on 11 July 2007, cancelled the contract of the 261 MW Kuther hydroelectric project in Chamba district to the D S Constructions that was awarded through competitive bidding.
D S Constructions had secured the Rs.1,500 crore project by offering the highest upfront premium of Rs.52 lakh per megawatt.
The allotment was cancelled because the company failed to achieve the set milestones and did not deposit the 50 per cent of the upfront premium of Rs.7.60 crore. It also did not agree to the condition of reverting the project back to the government after 40 years. It is learnt that the company had written to the government and sought some changes in the conditions. D S Constructions wanted that the upfront premium should be included in the project cost so that it was taken into consideration by the electricity regulatory commission while determining the generation cost.
Kuther hydroelectric power project was one of the three projects to be awarded through competitive bidding for the first time in the state. The other two were bagged by Brakel, a Dutch company for the Jhangi-Thopan (480 MW) and the Thopan-Powari (480 MW) projects in Kinnaur district.
Also See: