Illustrative image – not actual.Gail (India) has appointed Suz Tractebel of Belgium as technical consultant to carry out a study for the proposed pipeline from Myanmar to India, obviating Bangladesh en route.
Tractebel will prepare a detailed feasibility report, environment management plan and a rapid risk analysis report for the project.
The proposed pipeline will be routed through Mizoram, Assam, West Bengal and Bihar. The project also has the provision to transport gas from developing fields in Tripura and Assam. The Myanmar gas will be injected at Gaya in the proposed Jagdishpur-Haldia pipeline.
The basic contents of feasibility study are route selection, design parameters, system reliability, redundancy, safety, security, hydraulics, sizing, cost estimation, sensitivity analysis, risk analysis and mitigation measures, project construction schedule and project implementation strategy.
Also See:
Bangladesh sets conditions to allow India-Myanmar pipeline (14-Mar-05)