Illustrative image – not actual.Construction work on NTPC's 1,000 MW coal-based power unit at Ennore in Chennai is likely to begin by March 2007.
The Ennore project is being developed by NTPC-Tamil Nadu Energy Company Ltd, a 50:50 joint venture between NTPC and Tamil Nadu Electricity Board. The project coming up on an area of 1,100 acre of land will entail an estimated investment of Rs.4,000 crore. The project finance will be carried out with a debt-equity ratio of 70:30.
Unit 1 (500 MW) of the project is scheduled for completion by 2010-11 and the second unit by 2011-12.
Of the total power produced, 750 MW will be allotted to Tamil Nadu. The company has arranged for coal requirement, estimated at 5 million tonnes annually.