The construction work on Ega Theatre and Valluvar Kottam junctions has still not commenced, even after receiving a sanction more than two years ago.
Private consultants and corporations were optimistic that the 2.76 km flyover project, aimed at easing traffic and reducing the travel time between the two junctions, would be completed by the end of 2016.
The estimated cost of the project is Rs 350 crore.
Due to the massive acquisition of land the project requires, the current state of the project remains firmly on paper. Civic officials have been facing a lot of difficulty to acquire 38,000sq mtr of land to make way for the project.
The officials are facing opposition against land acquisition from commercial establishments and residents. In addition, it has no funds to support a compensation cost of Rs 1,000 crore, which is more than the cost of the project.
The officials are unsure as to when the work will begin. The project was planned to be constructed in three phases, each taking six months.