Concession agreement signed for Nagpur-Hyderabad SectionIllustrative image – not actual.

On 5 September 2007, National Highways Authority of India signed a concession agreement with Patel KNR Heavy Infrastructure (an SPV formed by Patel-KNR JV) for design, construction, development, finance, operation and maintenance of KM 230 (Islamnagar) to KM 278 (Kadtal) of Nagpur-Hyderabad Section on NH-7 in Andhra Pradesh.

The scope of work also includes strengthening of the existing two-lane on build, operate and transfer (BOT) Annuity basis. The project is a part of North-South Corridor under NHDP Phase-II.

The total project cost of this 53 km section is Rs.518.46 crore. The concession period will be 20 years including construction period of 24 months. The work has been awarded with semi annuity amount of Rs.44.37 crores payable to the Concessionaire by NHAI.