Completion time for wind power projects in Maharashtra extendedIllustrative image – not actual.

The Maharashtra state government has extended the time limit for completing wind power projects in the state from 31 December 2001 to 31 March 2002. These projects, with a total power generation capacity of 443 MW, would now have to be linked to the Maharashtra State Electricity Board (MSEB) by March 2002 end.

 

The state government has also directed MSEB to complete the 250 MW high tension centres for the evacuation of power generated from wind power projects. The government expects MSEB to complete the 150 MW substation by 31 March 2001 and the balance thereafter.

 

According to the state’s Chief Minister, Mr Vilasrao Deshmukh, power generated from wind power projects would be helpful for the state, which has a daily load shedding of at least 1,200 MW during the peak period. Besides, as MSEB had stopped buying power from Dabhol Power Company Ltd, power generated from wind based power plants had become essential.