Illustrative image – not actual.Talking to Projects Today, the promoter confirmed that at present work was underway and around 35 percent of the work has been completed.
The completion of the project is re-scheduled to November 2018 from December 2016. SS Constructions of Pune has been assigned as the contractor for completing the balance work.
The sugar unit with a capacity of 2,500 tccpd at Padal is being developed on 150 acre of land. The project has received environment clearance (EC) and re-commenced the work in January 2018. It was delayed in 2012 due to water issues.
The new sugar mill will also include a distillery unit with a capacity of 60 klpd and a 12 MW bagasse based captive power unit. Of the total cost of the project, 30 percent will be funded through internal accruals and the balance through bank loans.