The Parliamentary Standing Committee on Energy, in
its 12th report to the Parliament, has recommended a three-tier
clearance of power projects. The Committee felt that there were difficulties in
implementing the 'single window clearance' as there were multiple statutory agencies
involved. As a result there were inordinate delays in clearing power projects.
The Committee has suggested a system that involves
clearances of power projects at the Central, State and financial tie-up levels
in a time-bound programme so as to reduce the time lag between submission of
application and its final outcome for developing the project.
As an alternative, the Committee has also suggested
that the government should obtain all statutory clearances and then present the
project to the private sector for implementation.