Commissioning of tunnel for Kerala power project stayedIllustrative image – not actual.

On 25 May 2001, a division bench of the Kerala High Court refrained the State Government and the Kerala State Electricity Board from commissioning the 870-metre tunnel at the Koothungal hydro-electric power project in the State, until further orders.

 

The project was proposed to be commissioned on 27 May 2001.

 

KSEB had entered into an agreement with Coimbatore-based Indsil Electrosmelts Ltd for setting up the power plant at Koothungal. However, the company had not acted in accordance with the terms of the agreements and had not completed various construction works, including concreting and other mandatory works. The stay order was issued following a petition filed in the Court.