Commissioning of Hindupur plant gets delayed Illustrative image – not actual.

The commissioning of Berger Paints' plant, at Hindupur, in Andhra Pradesh, has been delayed due to the ongoing agitation over the formation of a separate state of Telangana.

 

The water-based paints and emulsions unit will have an initial capacity of 7,000 tpm which is scalable upto 20,000 tpm. The plant was supposed to commence operations this month, but the commissioning has been pushed back due to the Telangana agitation.

 

Government permissions, which include power connections, required at the fag end of the completion of the plant, have been delayed as there has been widespread absenteeism of officials due to the agitation.

 