Commercial production on RSPL greenfield soda ash unit to start by 2019Illustrative image – not actual.
RSPL has completed work on the sodium carbonate unit of five lakh tpa and work is underway on lignite-based captive power unit capacity of 50 MW. The greenfield unit is built on 1,000 acre of land in Jamnagar, Gujarat.

Projects Today has learnt that trial production has commenced at greenfield unit. In 2012, US-based construction and architecture firm, Jacobs Engineering, was appointed to provide engineering services for the project. But commencement of work on the project got delayed because of land and clearances issues.

In 2016, the promoters managed to get both the required land and environmental clearances (EC) for the greenfield project. The Rs 2,500 crore soda ash unit, funded largely through internal accruals, is now expected to start commercial production by March 2019.

Gannon Dunkerley & Company and Simplex Infrastructures are the civil contractors for the project.