NCC is expecting to start development and operation of Talaipalli coal block from 2019-20 onwards. Work on the project situated in the state of Chhattisgarh is expected to commence from FY 2018.
The company will make an investment of Rs 190 crore during the first year of its commercial operation.
NCC is targeting four million tonne of coal extraction and supply in its first year.
The project has been awarded to a consortium of NCC-BGR.
The project will be executed by a special purpose vehicle (SPV) to be formed between NCC and BGR Mining and Infra, with a sharing ratio of 51:49.
The mine will have a peak rated capacity of 18 million tpa to be achieved by the fifth year of commencement of operation.
The value of the project is Rs 25,071 crore.