Commercial production from Jindal's rail mill in May 2003Illustrative image – not actual.

The Rs.396 crore rail mill of Jindal Steel & Power Ltd is expected to start commercial production in May 2003. The unit has already begun trial production since February 2003, ahead of schedule.

 

The mill, which produces 120 m long rails, was acquired from Iscor (South Africa) and relocated in Raigarh.  The number of welds per km (paired lines) would drastically reduce from the present 160 (for a single rail of 12.5m) to just 17.

 

The company expects to generate annual revenue of Rs.1,200 crore, including export earnings, from the rail mill project.

 

Project Milestones

 

May 2001: Jindal Steel and Power Ltd (JSPL) signed a memorandum of understanding (MoU) with Chhattisgarh State Industrial Development Corp (CSIDC) for implementing the project in Chhattisgarh.   Advani-Oerlikon tied up with the Switzerland-based Schlatter for taking part in the long rails project.

 

December 2001: The company entered into a technical collaboration with NKK Corp. of Japan.

 

June 2002: Financial closure was achieved. Commercial production was delayed till April 2003, from the earlier envisaged December 2002.  The delay was attributed to the delay in shipment of critical equipment from Germany and Austria.

 

February 2003: Trial runs commenced.