Colaba-Bandra-Seepz Metro line tunnelling work partially completeIllustrative image – not actual.

The Colaba-Bandra-Seepz Metro line has completed nearly 10 percent of tunnelling for its underground corridor.

The 33.5 km corridor is being implemented by the Mumbai Metro Rail Corporation (MMRC), of this five km of tunnelling work has been completed across its alignment in the city.

The tunnelling is underway at four locations -- Azad Maidan, Vidyanagari (Kalina), Marol and Naya Nagar (Mahim) -- with eight tunnel-boring machines (TBMs) in operation.

The first TBM breakthrough will be achieved in the 4.15 km Marol-MIDC-Seepz (Package-7) section of the construction by September 2018.