Illustrative image – not actual.Colaba-Bandra-Seepz Metro corridor, also known as Metro-III, is likely to be delayed by at least a year due to stalling of decisions related to the project by the State Government.
Metro-III may be postponed due to delay in the formation of a special purpose vehicle (SPV) and appointment of the board of directors to execute the public transport project.
As these procedures are yet to be implemented, the Centre has withheld its share of Rs 160 crore. Even the Japan International Cooperation Agency (JICA) is willing to release funds, but is held back by lack of progress in the project.
The original date of completion of the Rs 23,136 crore project is December 2019.
The root cause of the problem is the failure to sign a memorandum of understanding (MoU) that will transform the Mumbai Metro Rail Corporation (MMRC) into a 50:50 joint venture (JV) between the State Government and the Centre. The JV MMRC will then be the SPV to execute the project.
The State is yet to approve the MoU for the joint venture even though the draft was sent on 30 September, 2013.
On September 16, the Mumbai Metropolitan Region Development Authority (MMRDA) had invited pre-qualification bids for detailed design and construction of underground stations and association tunnels. The process was supposed to be finalized by December 2013 so that it would be possible to invite bids by January.
The MMRDA has already twice extended the last date for submission of bid documents for this stage of the project.