Coimbatore’s car parking project delayedIllustrative image – not actual.

The Rs 31 crore multi-level parking project of the Coimbatore Corporation in Tamil Nadu is likely to take off only after the new government assumes office.

The project report had suggested automated parking lots on Cross Cut Road at Rs 32.99 crore, on D.B. Road at Rs 69.80 crore, and on Town Hall Road at Rs 28.84 crore.

The facility at Cross Cut Road would have five floors for parking cars, two floors for commercial space, and a basement for parking two-wheelers. The five floors could accommodate 316 cars and 350 two-wheelers in the basement.

In D.B. Road, there would be five levels of parking, two levels of commercial space, and a basement for two-wheelers. It would have 20 multi-level car parking elevators, and a commercial elevator. In Town Hall, there would be four levels of car parking space, and a two-wheeler parking facility in the basement.

The corporation would lease out the land to the highest bidder for 30 years to build the multi-level parking facility. During the lease period, there could be a revenue sharing model with the civic body.