Illustrative image – not actual.The proposed multi-crore expansion of Coimbatore International Airport has successfully secured approval from NITI Aayog and is currently awaiting final clearance from the Cabinet Committee on Expenditure.
Airport Director Mohammad Arif announced that the master plan requires 627 acres of land in addition to the existing 420 acres, bringing the total post-expansion footprint to over 1,047 acres. Of this, 621 acres have already been transferred to the Airports Authority of India (AAI). As part of long-term capacity enhancement, plans include constructing a terminal building, which will boost annual passenger handling capacity from 35 lakh to 1.20 crore.
Additionally, the airport is progressing with environmental clearances and preparing to roll out a 24-day "Yatri Seva Abhiyan" service camp to optimize passenger amenities.