Coastal Energen to raise funds to finance debt  Illustrative image – not actual.

Coastal Energen Private (CEPL), is planning to raise $300 million (approx Rs 1874.4 crore) through External Commercial Borrowings to refinance exist loans.


The company is setting up 1,200 MW coal-based power project at Tuticorin in Tamil Nadu with an investment of Rs 5,200 crore in two phases. The sharp drop in value of the rupee against the dollar may push up costs further for the project, which has been hit by delays in commissioning.


The project commissioning has been delayed by 15-16 months because of the time taken by lenders to sanction debt for cost overruns. While delay raises risks, the company has fuel supply agreements and the power purchase pact in place with all necessary clearances.


The delay in project commencement may put pressure on the principal repayments starting from December 2013. It may cause cost overruns mainly relating to interest expenses which are yet to be tied up.

 