Illustrative image – not actual.Coastal Energen, the power generating flagship company of Coal & Oil Group, has achieved financial closure for the Rs 3,450 crore debt for its 1,200 MW coal based power plant at Tuticorin in Tamil Nadu.
A total of 16 banks led by State Bank of India are lending to the project. The loan carries tenure of 15 years with an interest rate of 12 per cent.
L&T and Tata Projects have reportedly submitted their bids for Coastal Energen's 'Balance of Plant' contract worth Rs 1,500 crore. However, according to sources, the company is planning to split 'balance of plant' into various components and tender them out separately with the advice from Tata Consulting Engineers, in a bid to bring down costs.
The plant is expected to be commissioned within 36 months and has provision to expand upto 4,000 MW.