Coal projects face cost overrunsIllustrative image – not actual.

Seventeen coal projects, including those of Neyveli Lignite Corporation, Northern Coalfields, Bharat Coking Coal, etc are facing cost overruns. The original cost of these 17 projects totalled Rs.9170 crore. Now with cost overruns of Rs.10,325 crore, these projects are estimated to cost Rs.19,495 crore. These cost overruns have occurred due to several reasons such as delays in land acquisition, constraints in procuring equipment, etc.

 

Some of these projects are given below:

 

Company Name

Location

Cost (Rs.crore)

Proposed Date of Commissioning

Original

Revised

Neyveli Lignite Corp.

 

1336

1652

March 2003

 

Northern Coalfields

Dudhichua (Madhya Pradesh)

868

1271

March 2004

Bharat Coking Coal

Madhuband Washery project (Jharkand)

72

194

March 2001

Eastern Coalfields

Jhanjra (Jharkand)

184

403

March 2003

Neyveli Lignite Corporation

 

1032

1107

July 2001

Eastern Coalfields

Khottadih (Jharkand)

267

494

March 2003

South Eastern Coalfields

Dipka (Chhattisgarh)

533

580

March 2001

Central Coalfields

Parej (Jharkand)

116

162

March 2001

 