The Union Ministry of Power has asked the Union Ministry of
Coal to settle the fuel linkage issue of the fast-track Bhadrawati power
project in Maharashtra. The power ministry has said that the coal linkage issue
for the 1,000 MW counter guarantee project should be settled so as to avoid any
further delay in its implementation.
The power ministry was expected to settle the differences
between the MSEB and the coal ministry over the transportation of coal and also
the issue of premium. Coal India had demanded higher risk premium for the
supply of coal for the project. MSEB was, however, opposed to the idea since
this would increase the cost of power.
MSEB had also contented that the higher premium was not justified since
the coal mines were located just 40 km away from the project site, and hence
the risk of transportation was very less.
The project was promoted by the Mittals of the Ispat group,
French multinational EDF and Alsthom. However, EDF pulled out of the project
following the seven-year long delay in the implementation of the project and
the inability to finalise a coal supply agreement and to obtain an escrow cover
from the Maharashtra state government. According to the Mr.P.K.Mittal of the
Mittal group, the Mittals were looking out for a new joint venture partner.