Illustrative image – not actual.The Coal Ministry has allocated a coal block to SJVN, a JV between the Central Government and the Himachal Pradesh Government in West Bengal for its thermal power plant in Bihar.
The company has received the Deocha-Pachami mine for its upcoming 1,320 MW (2 x 660 MW) Buxar thermal power project, which is estimated to cost Rs 6,891 crore. The project will generate 9,090 million units of electricity at 85 per cent Plant Load Factor. SJVN will require 6.25 million tpa coal for the project, for which the company had signed an MoU with the Bihar Government in January 2013.
The allocated coal block is to be shared by the six state power companies along with SJVN. It has a reserve of 2,102 million tonne.
Apart from this, the company is also planning to commission its 412 MW Rampur hydro project in Himachal Pradesh and 47.6 MW Khirvire wind power plant in Maharashtra in FY14.
Related Link:
Project profile