Illustrative image – not actual.The Union Ministry of Coal is likely to cancel the Letters of Assurances (LoAs) for coal linkages issued to two proposed power projects in Orissa for their failure to achieve financial closure within six months of the issue of LoAs.
These power projects include GMR Kamalanga's 1,000 MW project at Kamalanga in Dhenkanal district and Ind Barath Energy Utkal's 750 MW (3x250) project at Sahajbahal in Jharsuguda.
The status of achievement of special milestones of as many as 23 proposed power projects in the country was reviewed by the Standing Linkage Committee (SLC) recently.
The Committee recommended that Coal India (CIL) or its concerned subsidiaries may issue a notice within 15 days to these project developers who have not achieved financial closure.
These developers need to respond within 15 days, explaining as to why the LoA issued to them should not be cancelled as they have failed to achieve financial closure within six months.