Coal linkage for Coal India arm Mahanadi Coalfields’ (MCL) 1,600 MW supercritical thermal power project in Sundargarh district of Odisha has been delayed.
Though coal linkage was pending, the preliminary work for the proposed power project has already begun. The company has also started the process of seeking environmental clearances.
MCL has acquired 800 acre for the project and water linkages are in place. Coal India board has also ratified the 2 x 800 (MW) thermal power plant at the mouth of a coalfield in the Mahanadi basin, which will mark the coal producer's foray into the power sector.
A special purpose vehicle (SPV), Mahanadi Basin Power (MBPL), has been incorporated as a wholly-owned subsidiary of MCL for setting up the project.