Coal India’s 89 ongoing projects delayedIllustrative image – not actual.
Eighty nine projects of Coal India are running behind schedule due to reasons such as delay in green clearances and law and order problems.

Of the 89 projects, 62 are mining projects and 27 are non-mining ones.

Out of 120 coal mining projects, 58 are running on schedule and 62 are delayed. Thirty four are running behind schedule on account of delays in getting forest clearances, and 17 are delayed because of land acquisition and associated R&R issues.

Seven projects are running behind schedule due to delay or discontinuance of work or non- participation in tender by the contractor; one project due to law and order problems; and three due to lack of railway infrastructure facilities for coal evacuation.

The non-mining projects are running behind schedule due to discontinuance of work by the contractor, law and order problems, acquisition of land, and associated problems of rehabilitation and forest clearances.

← All latest storiesBack to top →