Illustrative image – not actual.The Ministry of Coal has tasked Coal India to become a net zero emission energy compan. The MoU, also envisages setting up of 2,000 MW of thermal power generation across CIL’s subsidiaries. Solar projects will be set up over 15,000 acre on identified barren and reclaimed free land of Coal India and also at locations where free land is available.
The estimated cost for Coal India’s solar power generation is pegged at Rs 12,000 crore. The joint venture company will be scheduled to complete the proposed solar projects and thermal projects within 15 months and 60 months respectively.
The projects will be financed through debt equity, ratio of 70:30 as per the Central Electricity Regulatory Commission (CERC) norms. A concept paper has been initiated by both the companies to get clearance from their respective boards.