Coal handling plant at Paradip port to be delayedIllustrative image – not actual.

The completion of Paradip Port Trust’s 20 million tonne coal handling plant and the two-berth facilities, has been further delayed. The Rs.835.11 crore project is now scheduled for commissioning in September 2001.

 

The delay can be attributed to the delay in linkages to be provided by the Railways including wagons, loco engines and doubling of the Talcher-Paradip rail. Further, the work of the Railways complete with loop, receiving station, signalling and other facilities is not satisfactory. The nine km long and 1,800 mm wide conveyor system too, though installed by Larsen & Toubro, is not yet ready for use.

 

The project work, which started in May 1995, was expected to be completed in April 2000, at a cost of Rs.587.41 crore. However, due to the cyclone that hit the port in October 1999, the project work was delayed and completion was set for March 2001. This date has now been further postponed.