Illustrative image – not actual.The Union Shipping Minister, Mr
Vedprakash Goyal, will be dedicating to the nation, the mechanised coal
handling plant at the Paradip Port, on 11 September 2001.
The CHP is one of the largest in India in
terms of its handling capacity. It would provide a cost effective system of
loading and transporting coal to thermal plants in Tamil Nadu, where coal would
be handled by the Ennore Port.
The total cost of the project
(excluding interest during construction) is Rs.703 crore of which Rs.485 crore
was through ADB loan assistance.
This is the first system in India where
cargo can be unloaded from a moving train, on to a ship waiting at berth. The
plant provides for flexibility in that, if a ship is not at berth or is being
chartered by a different party, the coal can be diverted to the stack yard. The
stack yard, with a capacity of storing 6.5 lakh tonnes at a time, is powered by
two stackers with a capacity of 4,000 tonnes per hour.
The CHP would add around 20 million
tonnes per annum of handling capacity to Paradip Port, which already has a
capacity of 14 million tpa.
Mechanised CHP of Paradip Port: Features |
|
|
Project Cost |
Rs.703 crore |
|
ADB Loan |
Rs.485 crore |
|
Capacity |
20 million tpa |
|
CHP Capacity |
2 x 4000 tonnes per hour |
|
No. of Streams |
Two |
|
Size of Vessels to be
handled |
65,000 DWT (at 14.3 m depth) 90,000 DWT (at 15.8 m depth) |
|
Conveyor |
9 km |
On the same day, the port
authorities also commissioned two other general cargo berths on the western
side of the port. These berths have a capacity of 3 million tonnes each.