Illustrative image – not actual.The Jharkhand State Electricity Board's (JSEB) 1,980 MW Patratu coal based power project in Ramgarh district has been surrounded by uncertainties.
Patratu has an old power plant with 840 MW capacity, currently running at a very low plant load factor. In April 2010, JSEB had issued global tenders inviting EoIs from power players to develop a thermal power plant at Patratu with a capacity of 1,320-1,980 MW. Under the plan, the new plant was to be linked with the 400 million tonne Banhardih coal block. This block was to be developed by a JV company to be formed between the successful bidder of the project and JSEB.
JSEB is learnt to be in a legal tussle with Eastern Minerals and Trading Agency (EMTA), which was its JV partner for developing captive coal blocks allotted to JSEB. Unless the air on the state of the JV is cleared, it will be difficult for the state to give away the coal block to a private party for development.
Also, there is a possibility that the power plant may not come soon as the Union Ministry of Coal had released a list of 15 coal blocks which have not been developed since allocation to different parties. JSEB's Banhardih coal block is one of them.
Related Links:
Project profile