CMS Energy of US has threatened to pull
out of the 1,850 MW Ennore Power project for lack of co-operation and support
from the Indian government.
According to Mr William McCormick, CEO
of CMS Energy, the project has been in negotiation stage for several years with
little progress being made on implementation.
When CMS was selected as the foreign
partner for implementing the project, an assurance in the form of Sovereign
guarantee was provided. However, in the present scenario, there is little scope
for the project, or for any IPP project for that matter, to be given counter
guarantees. The US company would proceed with the project only if the promised
Central credit support were provided.
The 1,850 MW Ennore Power Project is
being jointly promoted by CMS Energy of US, Siemens of Germany and Grasim
Industries – each holding a 27 per cent stake in the company. The project, with
a total outlay of Rs.5,822 crore, is proposed to come up at Tiruvallur in Tamil
Nadu.