CMRS to begin safety checks on Versova-Andheri-Ghatkopar corridor Illustrative image – not actual.

The Commissioner of Metro Railway Safety (CMRS) will conduct the last safety check on the 11.4 km Versova-Andheri-Ghatkopar corridor (Phase-I of Mumbai Metro) which will commence on 18 April, 2014.

 

The safety check by CMRS is the last step of the safety certification process, which determines whether the railway line has complied with all technical rules and regulations and whether the line can be opened for public use.

 

The Versova-Andheri-Ghatkopar corridor has been undertaken by Mumbai Metro One (MMOPL). Once, the CMRS is satisfied with tests and trials, it will authorise MMOPL to open Phase-I for public use.

 

After receiving the approval from CMRS, the MMOPL will have to approach the Ministry of Railways to declare the line open for public use.

 

On 2 April 2014, Research, Design and Standards Organisation (RDSO) had issued its speed certificate for the stretch, after conducting speed trials on the line in February 2014.

 

On 4 April, the promoter had applied to the CMRS for safety certification of the stretch.

 

 The total cost of the Versova-Andheri-Ghatkopar (VAG) metro corridor (Phase-I) is Rs 2,400 crore.

 