CMRL viaduct construction at Alandur to be completed by December 2025 Illustrative image – not actual.

The elevated viaduct construction at Alandur, part of Chennai Metro Rail’s Phase II Corridor 5, is set for completion by December 2025. This corridor stretches from Madhavaram to Sholinganallur, passing through Alandur. On 19 June, 2025, Chief Minister MK Stalin inspected the ongoing construction work, including ascending one of the elevated structures for a detailed review.

The Alandur section involves a technically complex construction process known as the ‘balanced cantilever method’, chosen due to the high traffic density at the Kathipara junction. This method allows construction without obstructing regular traffic flow. Notably, the Alandur pillar stands 31 mtrs. tall and includes a 125-mtrs. radius curve. CM Stalin also inquired about progress on Corridor 3, which connects Madhavaram to Siruseri.

According to an official release, out of 80 segments planned for Corridor 5, 30 have been completed so far. Minister TM Anbarasan and other senior officials accompanied the Chief Minister during the inspection. The project aims to enhance public transport infrastructure in Chennai and reduce road congestion. Earlier, CMRL had imposed a fine of Rs one crore on a contractor and dismissed four employees following a girder crash at Ramapuram.

← All latest storiesBack to top →