Chennai Metro Rail (CMRL) has commenced the work of laying ballasted test track in Poonamallee depot for the Phase-II project which is underway in various parts of the city at a cost of Rs 61,843 crore.
This is the first time that a ballast track (with small crushed stones between rails) is laid in the Chennai Metro Rail system, as in both the phase-I and phase- I extension network, the authorities opted only for ballastless track.
The depot is crucial as it will primarily help in maintaining the trains operated between Poonamallee and Light House (Corridor-IV). The 820 mtrs. test track will be ready within six months, along with a stabling line and an inspection line too to be completed at the earliest. The test track will be completed on priority.
There will be a total of 24 tracks in this depot including stabling lines, inspection and repair lines and others. Of these, 13 lines will have ballasted tracks located within the depot and the rest of them ballastless and outside the depot.