Illustrative image – not actual.CLP Power India's plan to double its power plant capacity has come to a standstill, as it is not able to source sufficient gas. The expansion plan of Rs.3,500 crore at its power plant near Bharuch in Gujarat has been on hold for a year.
The company is weighing options to procure gas so that it can take its power capacity from 655 MW to 1,050 MW. The company had received the required environment clearance from the Gujarat Pollution Control Board (GPCB) in 2007.
Currently 60 per cent of the power plant's energy requirements are sourced from gas while 40 per cent is sourced from liquified natural gas (LNG). Gas is procured from players like Gujarat State Petroleum Corporation and Cairn Energy while LNG is procured from Petronet and Shell. For additional gas requirements, the company is in talks with Reliance, ONGC and Essar.